Job Life Cycle Process (JLCP) Task Matrix

Source: JLCP Main Tasks v121225.xlsx + JLCP Subtasks.csv
Total Tasks: 87 main tasks + 14 subtasks = 101 total
Last Updated: December 2025


Summary Statistics

MetricCount
Total Main Tasks87
Total Subtasks14
Independent Tasks30
Dependent Tasks56
Recurring Tasks19
Automation Tasks7

Tasks by Stage

StageTask Count% of Total
Pre-Construction4451%
Construction1922%
Safety & Compliance910%
Mobilization910%
Demobilization33%
Retainage33%

Tasks by Responsible Role

RoleTask Count
Project Accountant25
Project Manager24
Safety Coordinator9
Asst Project Manager8
Automation7
Operations Coordinator7
Other (shared/multiple)7

Pre-Construction Tasks (44 tasks)

#TaskResponsibleTypeDepends On
1Receive LOI or Contract from GC and ReviewSalesTask
2Submit Podio Project Intake FormProject ManagerTask
3Estimator, Sales Person, & PM Conduct Solo Job Intro Meeting2 stakeholdersTask
4Set-up Job in Google DriveAutomationAutomationTask #2
5Add new Job to Job ListingsAutomationAutomationTask #2
6Create Job Info SheetAutomationAutomationTask #2
7Create RFI Log (if needed)AutomationAutomationTask #2
8Create Submittal LogAutomationAutomationTask #2
9Create Vendor/Buyout LogAutomationAutomationTask #2
10Create Change Order Request LogAutomationAutomationTask #2
11Estimator Adds OST Takeoff PDFs to Office Google Drive FolderEstimatorTaskTask #3
12PM Fills out Job Info TemplateProject ManagerTaskTask #3
13Send LOI/Contract to Linda & Accounting for ReviewProject ManagerTaskTask #12
14Receive & Review LOI/ContractProject AccountantTaskTask #12
15(CCIP dependent) PM provides Estimated # of Man Hours for ProjectProject ManagerTaskTask #14
16Field Leak of Upcoming Job Scope from PM to DFO (director of field operations)Project ManagerTaskTask #3
17Negotiate Contract (if needed)Project Manager, Project AccountantTaskTask #14
18Send Signed Contract to GCProject Manager, OwnerTaskTask #17
19Enroll in Required Insurance + Request Bond if RequiredProject AccountantTaskTask #18
20Submit C3 documentation (conditional)Project AccountantTaskTask #18
21Enter Job into QuickBooksProject AccountantTaskTask #19
22Create Schedule of ValuesProject ManagerTaskTask #18
23Enter Schedule of ValuesProject AccountantTaskTask #19
24Add Project Spec to know if Textera or Procore is NeededProject AccountantTaskTask #14
25Determine Cost EstimatesProject ManagerTaskTask #18
26Enter Job Cost EstimatesProject AccountantTaskTask #24
27Create GC Job ContactsProject ManagerTaskTask #18
28PM Selects Vendors and Requests SignaturesProject ManagerTaskTask #18
29PM Returns Signed Quotes to VendorsProject ManagerTaskTask #27
30Create a Work Order for SubcontractorsProject ManagerTaskTask #28
30Upload Signed Vendor Quotes to Google DriveProject ManagerTaskTask #28
31Fill-out Tax Exempt FormsProject AccountantTaskTask #28
32Send Tax Exempt Certifications to VendorsProject AccountantTaskTask #33
33Request Reinforcement Shop Drawings from VendorAsst Project ManagerTaskTask #34
34Review Shop Drawings Internally, then Send Shop Drawings from Vendor to GCProject ManagerTaskTask #35
35PM compiles material list for project and ensures it is uploaded to the Project Drive folderProject ManagerTaskTask #28
36Pull Submittal Data from Vendor PortalsAsst Project ManagerTaskTask #37
37Pull Safety Data Sheets from Same PlaceAsst Project ManagerTaskTask #37
38Send SFA Submittals to GC/EngineerAsst Project ManagerTaskTask #37
39Resubmit Revised Submittals (as needed)Asst Project ManagerTaskTask #37
40Submit Safety Data SheetsAsst Project ManagerTaskTask #37
41Track Submittals in Submittal LogAsst Project ManagerTaskTask #37
42Confirm Approval of Submittals from GC/EngineerAsst Project ManagerTaskTask #38
43Schedule Precon MeetingProject ManagerTaskTask #44

Mobilization Tasks (9 tasks)

#TaskResponsibleTypeDepends On
1PM Requests CAD Files from GCProject ManagerTaskTask #18
2PM Requests Schedule from GCProject ManagerTaskTask #18
3PM Forwards CAD Files to Layout TeamProject ManagerTaskTask #46
4PM Receives & Reviews ScheduleProject ManagerTaskTask #47
5Conduct Internal Job Meeting w/ Sub(s) & Team (3 biz day advance notice)Project ManagerTaskTask #45
6Set-up Initial Job MobilizationOperations CoordinatorTaskTask #50
7Site Visit by OC and Foreman w/ SuperIntendentOperations CoordinatorTaskTask #50
8Create Job ScheduleOperations CoordinatorTaskTask #50
9Schedule Initial DeliveriesOperations CoordinatorTaskTask #50

Construction Tasks (19 tasks)

#TaskResponsibleTypeDepends On
1Review & Verify Sub/Vendor InvoicesProject AccountantRecurring
2Verify Receipts for Job CostsProject AccountantRecurring
3Track Quotes in QuickbooksProject AccountantRecurring
4Compiling Job Cost ReportsProject AccountantRecurring
5Track WEX Fuel LogsProject AccountantRecurring
6Verify Invoices w/out Quote/Purchase OrderProject ManagerRecurring
7Track Daily Reports & Technology(?)Project ManagerRecurring
8Track Owned EquipmentProject AccountantRecurring
9Report Certified Payroll + CCIP RequirementsProject AccountantRecurring
10Create Change Order Requests (As Needed) and SubmittalsOperations Coordinator, Project ManagerRecurring
11Submit Change Order RequestsProject ManagerRecurring
12Track Change Orders in Change Order LogProject ManagerRecurring
13Release Material OrdersOperations CoordinatorRecurring
14Order MaterialsOperations CoordinatorRecurring
15Order EquipmentOperations CoordinatorRecurring
16Distribute & Process Invoices from VendorsProject AccountantRecurring
17Initiate Payment ApplicationsProject AccountantRecurring
18Submit BillingProject AccountantRecurring
19Submit WaiversProject AccountantRecurring

Safety & Compliance Tasks (9 tasks)

#TaskResponsibleTypeDepends On
1Request 811 Line Locate RemarksSafety CoordinatorTaskTask #49
2Verify All Subcontractors have a Master Agreement On FileSafety CoordinatorTaskTask #29
3Initial 811 Line LocateSafety CoordinatorTaskTask #50
4Compose Safety FormsSafety CoordinatorTaskTask #50
5Submit Equipment Certifications to GCSafety CoordinatorTaskTask #50
6Submit SSSP to GCSafety CoordinatorTaskTask #50
7Upload the above to Project Drive Folder & Send Safety Deliverables to Ops Coordinator and ForemanSafety CoordinatorTaskTask #50
8Submit All Necessary Labor Credentials for Badging & Schedule Trainings to GCSafety CoordinatorTaskTask #50
9Book Out of Town Reservations (if needed)Safety CoordinatorTaskTask #50

Demobilization Tasks (3 tasks)

#TaskResponsibleTypeDepends On
1Review Punchlist Received by GCOperations Coordinator, Project ManagerTask
2Submit Warranty LettersProject AccountantTaskTask #62
3Submit Final Retainage BillingProject AccountantTaskTask #62

Retainage Tasks (3 tasks)

#TaskResponsibleTypeDepends On
4Scan Closeout Documents/Files to Job FolderProject AccountantTaskTask #62
5Check-Off Status Column for Job in Job ListingsProject AccountantTaskTask #65
6Move Job Folder to Back Office Shared Drive (Archived Projects?)Project AccountantTaskTask #65

Subtasks (14 total)

Parent TaskSubtaskDescriptionResponsible
Task #11.1Review $ AmountProject Manager
Task #11.2Review RetainageProject Manager
Task #11.3Review ScopeProject Manager
Task #33.1Project Notes w/ Vendor QuotesProject Manager
Task #33.2OST FileProject Manager
Task #33.3Bid FileProject Manager
Task #88.1Review Mix DesignsProject Manager
Task #88.2Review Shop DrawingsProject Manager
Task #88.3Review Product DataProject Manager
Task #1414.1Review to see if Certified Payroll is a requirementProject Accountant
Task #1414.2Review Insurance RequirementsProject Accountant
Task #1414.3Review OCIP/CCIP/ROCIP RequirementsProject Accountant
Task #8282.1Concrete Accessories/FormsOperations Coordinator
Task #8282.2Concrete MixOperations Coordinator