JLCP Dependency Flowcharts

Visual diagrams showing how tasks flow and depend on each other.


Legend

ColorMeaning
🟢 GreenIndependent task (can start immediately)
🟡 YellowDependent task (waiting on predecessor)
🔵 BlueAutomation task (runs automatically)
🟣 PurpleCross-stage dependency
🟠 OrangeRecurring task

Pre-Construction Dependencies

This is the most complex stage with 44 tasks and multiple dependency chains.

Contract & Setup Flow

🔍 Click diagram to expand

Vendor & Submittal Flow

🔍 Click diagram to expand

Mobilization Dependencies

🔍 Click diagram to expand

Construction Dependencies

🔍 Click diagram to expand

Key Dependency Chains

1. Contract Chain (Critical Path)

LOI → Job Info → Review → Negotiate → Sign → Insurance → QuickBooks

Owner: PM → ACC → PM+Owner → ACC

2. Submittal Chain

Select Vendors → Signed Quotes → Material List → Pull Submittals → Send to GC → Approval → Precon Meeting

Owner: PM → APM → APM → APM → PM

3. Safety Chain

Precon Meeting → Create SSSP → Submit SSSP → Approval → Post on Site

Owner: PM → SC → SC → SC → SC

4. 811 Locate Chain (Recurring)

Request 811 → Wait for Marks → Document → [Repeat every 2 weeks]

Owner: SC (recurring)