JLCP Dependency Flowcharts
Visual diagrams showing how tasks flow and depend on each other.
Legend
| Color | Meaning |
|---|---|
| 🟢 Green | Independent task (can start immediately) |
| 🟡 Yellow | Dependent task (waiting on predecessor) |
| 🔵 Blue | Automation task (runs automatically) |
| 🟣 Purple | Cross-stage dependency |
| 🟠 Orange | Recurring task |
Pre-Construction Dependencies
This is the most complex stage with 44 tasks and multiple dependency chains.
Contract & Setup Flow
🔍 Click diagram to expand
Vendor & Submittal Flow
🔍 Click diagram to expand
Mobilization Dependencies
🔍 Click diagram to expand
Construction Dependencies
🔍 Click diagram to expand
Key Dependency Chains
1. Contract Chain (Critical Path)
LOI → Job Info → Review → Negotiate → Sign → Insurance → QuickBooks
Owner: PM → ACC → PM+Owner → ACC
2. Submittal Chain
Select Vendors → Signed Quotes → Material List → Pull Submittals → Send to GC → Approval → Precon Meeting
Owner: PM → APM → APM → APM → PM
3. Safety Chain
Precon Meeting → Create SSSP → Submit SSSP → Approval → Post on Site
Owner: PM → SC → SC → SC → SC
4. 811 Locate Chain (Recurring)
Request 811 → Wait for Marks → Document → [Repeat every 2 weeks]
Owner: SC (recurring)
Related:
- jlcp-matrix.md — Full task table
- dependencies.md — How dependencies work