JLCP Dependency Flowcharts

Visual diagrams showing how tasks flow and depend on each other. Task numbers match the live Podio app.


Legend

ColorMeaning
🟢 GreenIndependent task (can start immediately)
🟡 YellowDependent task (waiting on predecessor)
🔵 BlueAutomation task (runs automatically)
🟣 PurpleCross-stage dependency
🟠 OrangeRecurring task

Pre-Construction Dependencies

The most complex stage. Split into two flows for readability. Automations (4–10) fire off the Podio Project Intake Form (Task 2). Task 9.1 (Fill Out Vendor / Subs List) follows the Vendor / Subs List Template automation. Task 20 (Submit C3 documentation) is now sequenced in order after the signed contract.

Contract & Setup Flow

🔍 Click diagram to expand

Vendor & Submittal Flow

🔍 Click diagram to expand

Mobilization Dependencies

🔍 Click diagram to expand

Safety & Compliance Dependencies

🔍 Click diagram to expand

Note: Safety tasks 57 (Compose Safety Forms), 59 (Submit SSSP to GC), and 60 (Upload Safety Deliverables) depend on Task 3 (Intro Meeting) — confirmed against the live Podio export — so safety prep starts right after the intro meeting rather than waiting on Mobilization. The remaining safety tasks (56 Initial 811 Locate, 58 Equipment Certs, 61 Labor Credentials, 62 Out-of-Town Reservations) depend on Task 51 (Conduct Internal Job Meeting).


Construction Dependencies

All 19 Construction tasks (69–87) are Independent and Recurring — none depend on one another; all regenerate on a weekly/monthly cadence while the Construction stage is active. They group into three domains:

🔍 Click diagram to expand

Key Dependency Chains

1. Contract Chain (Critical Path)

LOI (1) -> Job Info Template (12) -> Review (14) -> Negotiate (17) -> Sign Contract (18) -> Insurance + Bond (19) -> QuickBooks (21)

2. Submittal Chain

Select Vendors (28) -> Signed Quotes (29) -> Material List (38) -> Pull Submittals (39) -> Send to GC (41) -> Approval (45) -> Precon Meeting (46)

3. Safety Chain

Intro Meeting (3) -> Compose Safety Forms (57) / Submit SSSP (59) / Upload Safety Deliverables (60)

4. Mobilization -> Safety Chain

Schedule Precon (46) -> Conduct Internal Job Meeting (51) -> Initial 811 Locate (56) / Equipment Certs (58) / Labor Credentials (61)