Skip to main content

Pre-Construction Stage

This is where you win or lose the project.

Pre-Construction is the planning, permitting, and coordination phase. It's 75% of your project's success. Rush this stage and everything downstream suffers. Do it well and the rest is smooth sailing.


What Is Pre-Construction?

Pre-Construction (Pre-Con) is everything that happens BEFORE your crew sets foot on the job site to start work.

You're doing:

  • Reviewing contracts
  • Getting permits
  • Coordinating with the GC
  • Submitting documents
  • Answering RFIs
  • Planning logistics
  • Setting up safety
  • Collecting required documents

You're NOT doing:

  • Pouring concrete
  • Setting rebar
  • Running equipment

That comes later (Construction stage).


When Does Pre-Con Start?

Pre-Con starts the moment you create a project.

When you create a new project and set Current Stage Status to "Pre-Construction Active", tasks for this stage automatically populate.

New project with Current Stage Status = "Pre-Construction Active"


How Many Tasks in Pre-Con?

For Concrete division: ~46 tasks (the most of any stage!)

[NEEDS VERIFICATION: Does Drywall division have a different task count for Pre-Con?]

Pre-Con has the most tasks because there's SO much coordination work.

Pre-Construction stage page showing 46 tasks in Task Overview


Major Categories of Pre-Con Work

1. Contract & LOI Review

Make sure you understand what you're signing up for.

Tasks include:

  • Review LOI or Contract
  • Identify scope, exclusions, and deliverables
  • Flag any unclear items
  • Confirm pricing and payment terms

Why it matters: Misunderstanding the scope leads to disputes, change orders, and lost profit.


2. Permits & Compliance

Get legal approval to work.

Tasks include:

  • 811 Locate (Call Before You Dig) - REQUIRED for any digging
    • Submit locate request
    • Wait for utility marking
    • Document locate ticket
  • Badging - Get crew members badged for site access (if required by GC or site)
  • Site-Specific Safety Plan (SSSP) - Create or update safety plan for this job
  • Any local permits (building, grading, etc.)

Why it matters: You can't legally start work without these. Period.

Screenshot needed

Safety & Compliance tasks showing 811, Badging, SSSP - task list filtered to show safety-related Pre-Con tasks


3. Submittals

Submit your plans, materials, and methods to the GC for approval.

Tasks include:

  • Prepare shop drawings (if required)
  • Submit material specs
  • Submit installation methods
  • Wait for GC approval
  • Resubmit if rejected

Why it matters: You can't order materials or start work until submittals are approved.

Typical timeline: 1-2 weeks (depends on GC responsiveness)

Screenshot needed

Submittal-related tasks in Pre-Con - task list filtered to show submittal tasks


4. RFIs (Requests for Information)

Ask questions when the plans or scope aren't clear.

Tasks include:

  • Identify unclear items in plans
  • Draft RFI
  • Submit to GC
  • Wait for response
  • Document answer

Why it matters: Don't guess. If something's unclear, ask. Better to delay 3 days for an RFI answer than to do it wrong and redo the work.

Screenshot needed

RFI task with example RFI question - single RFI task detail page


5. Scheduling & Coordination

Figure out when you're working and coordinate with other trades.

Tasks include:

  • Get GC's master schedule
  • Identify your work windows
  • Coordinate with other trades (who's before you? who's after you?)
  • Create internal crew schedule
  • Order long-lead materials

Why it matters: You don't work in a vacuum. If the electrician is late, your pour might shift. Plan for it.


6. Document Collection

Gather everything you'll need for the project.

Tasks include:

  • Get site plans
  • Get soil reports (if applicable)
  • Get structural drawings
  • Get GC contact list
  • Get site access info (gate codes, parking, etc.)

Why it matters: You can't execute without the right info. Collect it all up front.

Documents & Logs field on project with uploaded files


7. Safety Setup

Make sure the job site is safe BEFORE work starts.

Tasks include:

  • Complete SSSP
  • Conduct pre-job safety meeting
  • Identify hazards
  • Set up site safety measures (barriers, signage, etc.)
  • Ensure crew has proper PPE

Why it matters: Safety isn't optional. Injuries cost time, money, and lives.


8. Logistics Planning

How is work actually going to happen?

Tasks include:

  • Plan equipment needs (what, when, how many)
  • Plan material delivery (where to stage, when to deliver)
  • Plan crew size and schedule
  • Plan site access and parking
  • Identify constraints (narrow roads, overhead power lines, etc.)

Why it matters: Day 1 on site should NOT be the first time you think about where to park the truck.


Task Dependencies in Pre-Con

Some Pre-Con tasks can't start until others are done. This is called task dependency.

Example:

  • Task: "Order rebar" (Dependent)
  • Depends on: "Submittal approved" (Independent)

You can't order materials until submittals are approved. Podio tracks this automatically.

When "Submittal approved" is marked Complete → "Order rebar" auto-advances to In Progress.

Screenshot needed

Dependent task waiting for prerequisite to complete - task with Pending status showing Dependencies field


Pre-Con Timeline

How long does Pre-Con take?

Short answer: 1-4 weeks, depending on complexity.

Factors that speed it up:

  • Simple scope
  • Responsive GC
  • No permits required
  • Standard materials (no custom fabrication)

Factors that slow it down:

  • Complex scope
  • Slow GC approvals
  • Permit delays
  • Custom materials with long lead times
  • RFIs that take weeks to answer

Don't rush it. A 3-week Pre-Con that's thorough beats a 1-week Pre-Con that's sloppy.


How to Know When Pre-Con Is Done

Pre-Con is "done" when:

✅ Contract/LOI is reviewed and understood
✅ All permits and compliance items are in place (811, badging, SSSP)
✅ All submittals are approved
✅ All RFIs are answered
✅ Schedule is locked in
✅ Materials are ordered (or ready to order)
✅ Safety is set up
✅ Crew is assigned and briefed
✅ Site access is confirmed
✅ You have everything you need to mobilize

Check your tasks: If all Pre-Con tasks are Complete (or the few remaining won't block Mobilization), you're ready to advance.

Pre-Construction stage showing completion metrics


Common Pre-Con Mistakes

❌ Rushing to Mobilization

Problem: "We got the contract, let's get on site!"
Result: Show up on site without permits, no approved submittals, crew doesn't know the plan. Chaos.

Fix: Stay in Pre-Con until you're ACTUALLY ready.


❌ Skipping RFIs

Problem: "I think this is what they want…"
Result: Do the work wrong, GC rejects it, you eat the cost of redoing it.

Fix: When in doubt, submit an RFI. Always.


❌ Not Tracking Dependencies

Problem: Try to order materials before submittals are approved.
Result: Order the wrong stuff, or order gets rejected, or you waste time waiting.

Fix: Respect task dependencies. Let Podio guide the order of work.


❌ Forgetting 811 Locate

Problem: Start digging without calling 811.
Result: Hit a utility line. Best case: work stoppage. Worst case: injury, fines, lawsuits.

Fix: ALWAYS call 811 before digging. It's the law.


❌ No Safety Plan

Problem: Show up on site without an SSSP or pre-job safety meeting.
Result: GC kicks you off site, or worse, someone gets hurt.

Fix: Safety first. Always.


Tips for Crushing Pre-Con

1. Start Day 1

Don't wait. As soon as the project is created, dive into Pre-Con tasks.


2. Batch Similar Tasks

Example: Do all your document requests in one email to the GC instead of 5 separate emails over 5 days.


3. Follow Up Relentlessly

Waiting on a submittal approval? Follow up every 2-3 days. Waiting on an RFI answer? Follow up. Don't let things sit.


4. Use Task Notes

When you hit a blocker, add a note to the task:

"Waiting on GC to approve submittal. Emailed 1/15, followed up 1/18. Still pending."

This creates a paper trail and helps the next person understand what's happening.

Screenshot needed

Task with notes showing status updates - task detail showing activity/notes section with updates


5. Mark Blockers Clearly

If a task is blocked (waiting on someone else), note it. Don't let it disappear into the pile.

[NEEDS VERIFICATION: Is there a "Blocked" status option for tasks, or do you just add notes?]


6. Communicate with the Team

Pre-Con isn't a solo job. The PM, OC, FOCS, and Foreman all need to be in sync.

Use Podio comments on tasks to loop people in.
Have a Pre-Con kickoff meeting to align everyone.


7. Don't Advance Until Ready

You'll feel pressure to move to Mobilization. Resist if you're not ready.

Ask yourself:

  • Do I have all permits?
  • Are submittals approved?
  • Is the crew ready?
  • Do I have materials ordered or ready to order?
  • Is the schedule locked?

If ANY answer is no → stay in Pre-Con.


Pre-Con Checklist

Before advancing to Mobilization, verify:

  • Contract/LOI reviewed
  • 811 Locate submitted and completed
  • Badging completed (if required)
  • SSSP created and submitted
  • All submittals submitted and approved
  • All RFIs submitted and answered
  • GC schedule received and understood
  • Crew schedule created
  • Materials ordered (or ready to order upon Mobilization)
  • Site plans and drawings collected
  • Site access confirmed (gate codes, parking, etc.)
  • Pre-job safety meeting scheduled or completed
  • Foreman briefed on scope and plan
  • Equipment needs identified
  • All Pre-Con tasks are Complete or blocking items are documented

What Happens After Pre-Con?

Once Pre-Con is done, you advance to Mobilization.

Read more: Mobilization Stage


Related Docs:


Remember

Pre-Construction is 75% of project success.

Invest the time here. Plan well. Coordinate thoroughly. Get your ducks in a row.

The 30 minutes you spend now writing an RFI saves you 3 days of rework later.

The 2 hours you spend reviewing the contract now saves you from a costly dispute later.

The 1 week you spend waiting for permit approval now saves you from getting shut down on site later.

Do Pre-Con right. Everything else gets easier.